Coal Handling Plant Performance Test

Posted in: , on 31. Dec. 2011 - 10:08

Coal handling performance test procedure ( pg test)

Dear hounourable forum team

A very happy and prosperous new year to you all.

Recently we have commissioned a 800 tph coal handling plant for a thermal power plant. in the process of handling over we need to submit performance test reports as a document.

I need the help of the forum in sharing any formats of coal handling performance test reports.

thanks

Re: Coal Handling Plant Performance Test

Posted on 1. Jan. 2012 - 04:34

Dear Shri Pappu,

The coal handling plant will be comprising of numerous equipment, mechanical, electrical and instrumentation.

For each of these equipment, the contract specification (between you and your buyer) must be stipulating the guaranteed parameters, as to be demonstrated during commissioning test. You have to create log book incorporating the test procedure and the parameters, in concurrence with the buyer.

Such log book will also mention duration of test, remedial measure for interruption and inadequate performance if any for concerned equipment etc.

Regards,

Ishwar G Mulani.

Author of Book : Engineering Science and Application Design for Belt Conveyors.

Author of Book : Belt Feeder Design and Hopper Bin Silo

Advisor / Consultant for Bulk Material Handling System & Issues.

Pune, India.

Tel.: 0091 (0)20 25871916

Perfomance Of Coal Handling Plant

Posted on 5. Jan. 2012 - 07:20
Quote Originally Posted by pappuView Post
Coal handling performance test procedure ( pg test)

Dear hounourable forum team

A very happy and prosperous new year to you all.

Recently we have commissioned a 800 tph coal handling plant for a thermal power plant. in the process of handling over we need to submit performance test reports as a document.

I need the help of the forum in sharing any formats of coal handling performance test reports.

thanks

Dear Pappu,

Normally aggreement has a perfomance guarantee clause.

Each element will have perfomance guarantee.

Above all an overall perfomance guarantee clause also will be provided.

A typical agreement states,

1.An Overall Perfomance at the rated out put of 800 TPH for 4 hrs ( ie 3200 tons in 4 hrs contonuous operation with out any break)

2.An overall perfomance for 72 hrs at 80% system efficiency.This may be fixed taking into consideration the working hrs permitted per day(20hrs etc)

Narayanan Nalinakshan.