Fortescue Metals: USD 2.6 billion Stage 2 Development of Iron Bridge Magnetite Project approved

Edited by mhd on 3. Apr. 2019
Fortescue Metals Group subsidiary FMG Magnetite and its joint venture partner Formosa Steel IB have approved the development of Stage 2 of the Iron Bridge Magnetite Project. The Stage 2 development includes a wet ore processing facility with a capacity 22 million mtpa, a 135 km concentrate pipeline, as well as port handling facilities including concentrate dewatering, covered storage and reclaiming/conveying to existing port outload circuits. Delivery of first ore expected in the first half of calendar year 2022.
wp_2483.jpg
The ore processing facility of the large scale pilot and demonstration plant at Fortescue Metals' Iron Bridge Project. (Picture: Fortescue Metals Group Ltd.)

The Iron Bridge Magnetite Project, located 145 km south of Port Hedland (WA), Australia, is expected to produce the equivalent of 20 million dry metric tonnes of magnetite ore per year at full operational capacity. The Stage 2 development, with total capital costs of USD 2.6 billion, follows the USD 0.5 billion investment in the successful Stage 1 construction of large scale pilot and demonstration plants which have validated key equipment and magnetite production processes for the full-scale Stage 2 ore processing facility.The Project is owned through an Unincorporated Joint Venture (UJV) between FMG Iron Bridge Ltd. (FMG IB) (69%) and Formosa Steel IB Pty. Ltd. (Formosa) (31%). FMG Magnetite Pty. Ltd. is a subsidiary of FMG IB, a Hong Kong registered company owned by Fortescue Metals Group Ltd. (Fortescue) (88%) and a subsidiary of Baosteel Resources International Company Limited (Baosteel) (12%).Fortescue’s Chief Executive Officer, Elizabeth Gaines said, “The Iron Bridge Project holds Australia’s largest JORC compliant magnetite resource supporting a long mine life. The successful delivery of the Project by the joint venture partners is underpinned by Fortescue’s unparalleled track record and capability in safely developing and operating major iron ore projects in the Pilbara.”“The Project is well progressed and ready for detailed design and execution with the majority of key approvals already in place. The innovative design, including the use of a dry crushing and grinding circuit, will deliver an industry-leading energy efficient operation with globally competitive capital intensity and operating costs,” Ms Gaines said.

Stage 2 Development

Stage 2 development of the Project includes:

  • 22 million wet metric tonnes per annum (wmtpa) ore processing facility
  • Airstrip and expanded village
  • 195 km Canning Basin water pipeline
  • 135 km concentrate pipeline to Fortescue’s Herb Elliot Port facility in Port Hedland and return process water pipeline
  • Port handling facilities including concentrate dewatering, covered storage and reclaiming/conveying to existing port outload circuits

The Project requires up to 225 megawatts of power which will be delivered by low cost power transmitted from a mix of existing and new generation sources in the Pilbara. Fortescue is responsible for delivering the power requirements inclusive of latent capacity transmitted from Fortescue’s Solomon power station, together with new generation and transmission which may involve third party providers and supply.

Key Features

Key features of the location, design and construction of the mine and infrastructure are as follows:

  • Ore stockpiles and waste dumps are located to the east and west of the mine and make use of natural valleys to store the life of mine (LOM) volumes.
  • The ore processing facility will be located approximately 1.5km southwest of the mine, with efficient positioning of the run of mine (ROM) pad and primary crushing hub.
  • Secondary crushing/screening and coarse ore stockpiles are located part way between the ROM pad and ore processing facility to minimise earthworks, conveyor angles and building heights.
  • The tailings storage facility is located in a natural valley north of the mine, with capacity to store the LOM tailings. This location slopes away from the mine and will be constructed using down-stream methodology.
  • Administration, warehousing and light and heavy vehicle workshops are co-located with the ore processing facility to maximise efficiency of operations.
  • The concentrate and return water pipeline corridor takes advantage of Fortescue’s existing rail corridor for 100 km of its 135 km length. The 195 km water supply pipeline from the Canning Basin borefield follows the most direct route to site.
  • The construction and operations villages are located approximately 4 km from the mine site.
  • The airstrip is located approximately 20 km west of the mine site on the most suitable flat land and is close to the mine access road and Great Northern Highway.

(Source: Fortescue Metals Group Ltd.)