Re: Fly Ash Pneumatic Conveying Problem
How many bends are there in the first 50 m ??? ■
Re: Fly Ash Pneumatic Conveying Problem
Dear kevinjcg
I calculated your test installation and found the following result:
pressure (baro) tons/hr
2,5 13
2,25 13
2,00 12
1,75 11
1,50 10
1,25 9
1,00 8
0,75 6
0,50 4
You can notice that the pressure increase significantly although the flow rate of the flyash changes very little.
This means that a little bit of fly ash extra into the air flow will increase the pressure very much.
By the preesure increase, the air velocity will eventually drop below the suspension velocity and a blockage is created.
That is presumably what happened in your installation.
OVER FEEDING THE PIPELINE
Also opening the outlet valve at 0,4 MPa (4 baro if I am correct) will overfeed the pipeline instantaniously and lead to a blockage in the first section after the outlet.
You may try to start conveying at abeginning pressure of f.i. ,5 baro and keeping the convey pressure below 2 baro, by controlling the feeding.
succes fro
Teus ■
Teus
Blow Tank Contol
How do you control the discharge rate of fly ash from your silo (blow tank)?
If all of your air is directed into the bottom of the silo to fluidise the fly ash you will only ever block such a long pipeline. Part of the supply air must by-pass the silo and be fed into the conveying pipeline as close to the top of the silo as possible. This by-pass, or supplementary, air will dilute the high concentration of fly ash leaving the silo to a value that will be possible to convey through the length of the pipeline with the pressure available. The discharge rate of any material from any blow tank is infinitely controllable by means of this air proportioning.
The concentration of the material discharged from a blow tank must be balanced by the conveying line pressure gradient. Too high a concentration and you will block the pipeline. Too low a concentration and it will convey, if the conveying air velocity is high enough, but you will not utilise all the air supply pressure that you have available.
If your pipline is 410 m horizontal and 45 m vertically up, with bends, and your air supply pressure is 100 psig your available pressure gradient for conveying will be about 12 mbar/m. A pressure gradient of 12 mbar/m should convey your fine fly ash at a solids loading ratio of about 50 and so the volumetric flow rate of your air supply should be satisfactory. You should achieve about 15 tonne/h through your pipeline with an air supply pressure of 0.7 Mpa. ■
Thanks
thanks for your reply
three bypass are used to connected to conveying pipeline, the by-pass entry separately is 60,200,300, that indicate the distance from entry of fly ash to entry of by-pass air, the by-pass air pressure is about 0.6mpa, when conveying ,we find there is still blockage in first 50m. from my view, i think it is hard to contral the discharge rate of fly ash from silo, only pressure of silo is avaiable, can i have other choice ?
regards
to David Mills
we have the handbook of your writingneumatic conveying design and guildline , we refer to that book , it can provide many experiences to design, thank you .
■
Re: Fly Ash Pneumatic Conveying Problem
there are 7 bends in first 50m and about 6m incline pipeline, the angle is about 11, these bends are essential to layout,so i think there is too much bends than safe conveying in first 50m, but having other mothed to solve blockage ?
■
Re: Fly Ash Pneumatic Conveying Problem
we try to start conveying when silo pressure is 0.2mpa, finding there is a still blackage , so we have to add a by-pass in 20m distance to fly ash discharge , that is very adverse ,because the bends wear out in one month .
■
Re: Fly Ash Pneumatic Conveying Problem
Dear kevinjcg
I recalculated your installation from 7 bar(o) down and found the following results :
Convey length = 455 m Nu of bends= 8 Pump vol = .1 + .1 m^3/s
q-convey = 0.10 m^3/s Dia begin = 80 mm Dia end = 100 mm
Kettle volume = 2.0 m^3 Cement vol.= 1.5 m^3 C-Vessel = 500 tons/hr
Kettle cement content = 1.0 tons Pipevolume = 2.71 m^3
Pipeline Syst. /Nr of Req.kettle
Press. Cap. mu Cap. /kettles fact. v-begin v-end kWh/ton res.time
7.000 21 49 15 / 10.3
Pneumatic conveying is possible at 1 bar(o).
The loading ratio is calculated as 49 kg/kg, which matches the value of Dr Mills
However this calculation assumes all the air going through the pipeline from the beginning to the end.
No air is by passed to a point further in the pipeline, as this would reduce the velocity and also increasing the local loading ratio before that injection point .
This will cause higher pressure drops and eventually choking
As only a small change in material feeding causes a big change in conveying pressure, the accuracy of the feeding control is very important
The cause of the choked pipeline must be too much material in the pipeline.
This can only be controlled by bypassing the convey air around the kettle.
This can be done by a manual valve as this is only a test installation.
In practice it should be done with an automatic regulating valve based on compressor pressure
Try to start conveying as follows.
open the manual by pass valve
pressurize the kettle to approx . 0,5 bar(o) (0,05 Mpa)
open the outlet valve
wait for approx 2 to 2,5 minutes (residence time of a particle can go up to 106 sec) until stable conveying occurs.
If the convey pressure can be increased gradually close the by pass valve.
After each new setting wait for stable conveying.
This can also be done with the opening pressure for opening the outlet valve
Also notice the difference in energy consumption/ton at different convey pressures
(this calculation is based on the use of a screw compressor)
Success
teus
Teus
Re: Fly Ash Pneumatic Conveying Problem
Sorry for an error in my message.
It should read " Pneumatic conveying is possible at 7 bar(o)"
------------
teus ■
Teus
Re: Fly Ash Pneumatic Conveying Problem
thanks for your reply
to Teus
you said , add a auto regulating valve in by-pass pipeline which near the fly ash discharge, that is a good idea, but start conveying when kettle pressure is 0.05Mpa, it is so long pipeline , fly ash will settle in pipe bottom although opening the auto regulating valve ,and also there are 7 bends in first 50m, thepressure is too much, that is feasible?
regards
■
Re: Fly Ash Pneumatic Conveying Problem
dear kevinjcg
starting conveying is assumed on an empty pipeline .
As soon as conveying starts there is airflow in the pipeline mixed with fly-ash
The maximum pressure in the blow tank is reached when the complete pipeline is filled with flowing fly-ash mixed with air with the maximum, regulated, loading ratio.
To start the next cycle of discharging , the pipeline must be purged empty, until all the fly-ash is removed.
This can be monitored on the pressure in the blow tank by reaching the “empty pipeline pressure”
Discharging at low pressure means a low loading ratio, little product resistance and because of the low pressure, higher air velocities.
As this is a very long pipeline, designed for a high pressure, this installation will always be very sensitive for choking and will require a very accurate by-pass control.
Note: your installation is designed for 7 bar(o), which should require a step up in diameter of approx. 1,7x instead of 1,25x, for optimal pneumatic conveying This to keep the air velocity just above the sedimentation velocity at any location in the pipeline
Pneumatic conveying might be a simple principle, it is not a simple art.
PS I tried to insert a drawing in this message, but that failed.
succes ■
Teus
Thanks For Your Reply
Dear Teus
we can monitor the pressure in blow tank, in trial we purge the pipeline after conveying twice, how much the blow tank pressure is when start conveying which is optimal do you think?
also ,we will think to add a by-pass around the blow tank, but how much is the pressure of by-pass which is avilable? air from bypass will dilute concentration of solid.
regards
■
Re: Fly Ash Pneumatic Conveying Problem
Dear kevinjcg
you can start conveying at any (low) pressure you want. If it results in a too low continuous discharge pressure at a certain setting of the by pass valve (called “extra air”) you can increase f.i the opening pressure for the next run.
May be you have to open the “extra air valve” again a little.
The stability of the pneumatic discharge-conveying is a result of the combined settings of opening pressure and extra air.
Start with a low opening pressure (f.i. 0,5 bar(o)) and an open “extra air valve”.
You are not by-passing pressure around the blow tank, but you are bypassing air-volume.
The less air goes through the blow tank, the less fly-ash is taken from the tank and the lower the loading ratio will be, resulting in a lower convey pressure.
The intention is to dilute the concentration of the mixture to prevent choking.
The trick is to find the maximum loading ratio, whereby the pneumatic conveying works without choking and keeping it that way.
An automatic “extra air valve” can do that for you
Success ■
Teus
Re: Fly Ash Pneumatic Conveying Problem
Your blow tank with no bypass air sounds like a high pressure single plug type system but then your conveying pipe diameter is bit small and batch size bit high. You are on the right track now ,bypass air on the blow tank is essential for a this type of system. Avoid putting bypass air in conveying line it just increase the velocity / wear in the system and could also reduce solid flowrate.
In the mean time u could try conveying flyash in single plug mode but using smaller amount per batch. Start with 175 kg/ batch at 3-4 barg and keep increasing/ decreasing the batch size until the optimum point is reached. This system is normally used with a doom valve as it requires higher number of cycles + there is higher wear in the system due to blowdown. But sicne it is a test plant no harm in trying !!! ■
Thanks
thanks for your reply
i think it is essential to bypass to pipeline in so long pipeline, also, it is necessary to bypass to blow tank, so diameter of pipe bore is small, so I think bore 108mm can be used, but using three bypass ,as supplementary to pipeline is good? distance is 60m,200m, 300m, and how much is the pressure ?
regards
■
Re: Fly Ash Pneumatic Conveying Problem
If you put bypass air after the blowtank it will reduce the solids flow rate which will result in lower system pressure drop. You will then not need injection points on the conveying line. In any case uncontrolled amount of air injection into the conveying line is always a big NO. ■
Re: Fly Ash Pneumatic Conveying Problem
dear kevinjcg
please can you give the following information when you are injecting supplementary air into the pipeline at f.i. 300m after the blow tank.
-air volume through the blow tank
-air volume by passing the blow tank
(air volume through the blow tank + air volume by passing the blow tank = air volume entering the pipeline at the beginning)
-air volume injected at 300 m distance from the blow tank
Using all the data already known this enables me to calculate the effect of such a trial.
best regards ■
Teus
Thanks
thanks for your relpy
Dear mantoo
yes, supplementary air will lower mass flow rate, but if we not using supplementary,there is a blackage, because we only estimate the volume of fly ash in blow ,there is not weight meter,
only fly ash is of about 75% of blow tank , starting conveying .or else ,using timer to control the fly ash in blow tank, that is bad .
so can I do ?
regards
Dear Teus
air volume through the blow tank is about 20~30m^3/patch, supplementary air ,we not using flow meter, only knowing the pressure of three bypass, about 0.6mpa, so can I do ?
regards
■
Re: Fly Ash Pneumatic Conveying Problem
dear kevinjcg
As you can see from previeous calculations, I assumed 0,1 m3/sec (6 m3/min) free air delivery from the beginning of the pipeline to the end,
If you set the pressure of the by passes at 6 bar, not knowing the injected air volumes, I cannot calculate the system because the velocities, loading ratio, product resistence etc cnnot be calculated.
Airflow should be known at every location in the pipeline.
My advise is to start testing the installation with the available air used from the beginning of the pipeline.
do not give up
all for now ■
Teus
Thanks
Dear Teus
thanks for your reply
i think that is no solution to calculate without volume of air, but did you think we can start conveying with only one bypass around blow tank,that means no using other three bypass? if that can do ,so how much is the blow tank is good for conveying?
best regards
■
Re: Fly Ash Pneumatic Conveying Problem
dear kevinjcg
yes you must be able to convey with only a (controllable) air by pass around the blowtank.
The total amount of air flow I already indicated in my answer dd 22nd of October 2005.
0,1 m3/sec # 6 m3/min. (based on your earlier information
The capacity is given in the table in that answer.
Maybe you should type this table out on your computer and repair the table, then it will be clear(er)
13 tons/hr at an average pressure of 5 bar is expected.
Use your common sense during trials s.a. :
lowering loading ratio decreases pressure drop and capacity and reduces the chance of choking. It also increase the velocities-
success ■
Teus
Re: Fly Ash Pneumatic Conveying Problem
If all of your air is directed into the bottom of the silo to fluidise the fly ash you will only ever block such a long pipeline. Part of the supply air must by-pass the silo and be fed into the conveying pipeline as close to the top of the silo as possible. This by-pass, or supplementary, air will dilute the high concentration of fly ash leaving the silo to a value that will be possible to convey through the length of the pipeline with the pressure available. The discharge rate of any material from any blow tank is infinitely controllable by means of this air proportioning.
The concentration of the material discharged from a blow tank must be balanced by the conveying line pressure gradient. Too high a concentration and you will block the pipeline. Too low a concentration and it will convey, if the conveying air velocity is high enough, but you will not utilise all the air supply pressure that you have available.
If your pipline is 410 m horizontal and 45 m vertically up, with bends, and your air supply pressure is 100 psig your available pressure gradient for conveying will be about 12 mbar/m. A pressure gradient of 12 mbar/m should convey your fine fly ash at a solids loading ratio of about 50 and so the volumetric flow rate of your air supply should be satisfactory. You should achieve about 15 tonne/h through your pipeline with an air supply pressure of 0.7 Mpa.
KA Dr David mills
Dear sir
I am doing one practical project in dense phase conveying system for indian fly ash. I was wondering about the advantage of bypass pipe technology in dense phase conveying syste. Apparantly in indian context , in almostall power plant teh pipe-inpipe techology is gaining its importance for fly ash pneumatic conveying system . In thsi technology where in there is a small pipe (having the hole at regular interval) air flow is through this small pipe
Please comment on below and rectify in my understanding .
My understanding is , teher is energy saving comparively for a reason as teh , pressure required for a short plug is less than pressure required for long plug. In pipe in pipe technology , since the air is being inserted at certain distance which maintains teh plug length distrubution
2) Secondly in pipe in pipe the permiability and air retention will be higher for a reason i dont no . pelase explain
3) Indeed there is reduction in area of conveying pipe and incerase in wall friction , but it seems teh advantage in this case plays a stronger influence over teh disadvantages of reducing the area. Please comment
Sir other than this , please explain why this technology been adopted and what is teh major significance in regard of pressure gradiant and air flow ■
Re: Fly Ash Pneumatic Conveying Problem
starting conveying is assumed on an empty pipeline .
As soon as conveying starts there is airflow in the pipeline mixed with fly-ash
The maximum pressure in the blow tank is reached when the complete pipeline is filled with flowing fly-ash mixed with air with the maximum, regulated, loading ratio.
To start the next cycle of discharging , the pipeline must be purged empty, until all the fly-ash is removed.
This can be monitored on the pressure in the blow tank by reaching the “empty pipeline pressure”
Discharging at low pressure means a low loading ratio, little product resistance and because of the low pressure, higher air velocities.
As this is a very long pipeline, designed for a high pressure, this installation will always be very sensitive for choking and will require a very accurate by-pass control.
Note: your installation is designed for 7 bar(o), which should require a step up in diameter of approx. 1,7x instead of 1,25x, for optimal pneumatic conveying This to keep the air velocity just above the sedimentation velocity at any location in the pipeline
Pneumatic conveying might be a simple principle, it is not a simple art.
PS I tried to insert a drawing in this message, but that failed.
succes
To Mr Teus
Sir, there is a distance limitation in vaccum conveying system, what is that limitation (may be in terms of distance) I got to size the fly ash conveying system in vaccum mode system for 35TPH at distance of 250mtr 5 bends. Now if i maintain the pickup and terminal velocity (16m/s & 27m/s respectively) to acceptable level and resulting volume with pressure gradiant is x m3/hr @ 16in HG. Now since teh same volume and pressure rating of vaccum equipment is available in the market , then why shouldnt i gp for it? ■
Re: Fly Ash Pneumatic Conveying Problem
Dear kj,
In vacuum conveying, the available pressure drop is 1 bar.
However, at 1 bar vacuum, the air mass flow becomes zero and then there is no pneumatic conveying possible.
Vacuum cement unloaders are designed for a vacuum of approx. 0.75 bar, which is close to the choking condition.
The vacuum is related to the vacuum conveying length, as the length determines the vacuum.
The maximum vacuum conveying length is therefore a function of the design vacuum.
I designed your system for 4 pipe sizes and found the following:
Pipe 8”/10”
Vacuum pump 0.75 m3/sec
32 tons/hr – 5500 mmWC vacuum
Pipe 10”
Vacuum pump 0.75 m3/sec
35 tons/hr – 2678 mmWC vacuum
Pipe 10”/12”
Vacuum pump 1.0 m3/sec
35 tons/hr – 2205 mmWC vacuum
Pipe 12”/14”
Vacuum pump 1.4 m3/sec
35 tons/hr – 2606 mmWC vacuum
If the equipment is available on the market, as you state, then there is no reason to ignore that.
Have a nice day
Teus ■
Teus
Re: Fly Ash Pneumatic Conveying Problem
In vacuum conveying, the available pressure drop is 1 bar.
However, at 1 bar vacuum, the air mass flow becomes zero and then there is no pneumatic conveying possible.
Vacuum cement unloaders are designed for a vacuum of approx. 0.75 bar, which is close to the choking condition.
The vacuum is related to the vacuum conveying length, as the length determines the vacuum.
The maximum vacuum conveying length is therefore a function of the design vacuum.
I designed your system for 4 pipe sizes and found the following:
Pipe 8”/10”
Vacuum pump 0.75 m3/sec
32 tons/hr – 5500 mmWC vacuum
Pipe 10”
Vacuum pump 0.75 m3/sec
35 tons/hr – 2678 mmWC vacuum
Pipe 10”/12”
Vacuum pump 1.0 m3/sec
35 tons/hr – 2205 mmWC vacuum
Pipe 12”/14”
Vacuum pump 1.4 m3/sec
35 tons/hr – 2606 mmWC vacuum
If the equipment is available on the market, as you state, then there is no reason to ignore that.
Have a nice day
Teus
Sir
1) As per your calculation vacum pump for 0.75m3/sec @5500mwc is available in market . But to get better understanding , what is the exactly disadvantage in vaccum conveying system , if the equipment is available. I know and can make a qualified guess of vaccum having disadvantages in long distance , but in what sense?
2) For a calculated suspension velocity as you taught , how to calculate pickup velocity in vaccum conveying system. Please specy the factor to be used ■
Re: Fly Ash Pneumatic Conveying Problem
Dear kj,
1)Compare the vacuum calculations with the pressure calculation for the same project.
250 m conveying length
5 bends
Capacity 35 tons
pipe size 6” (vacuum 10”)
Air displacement pump 0.3 m3/sec at 1 bar (vacuum 0.75 m3/sec at 0.2678 bar vacuum)
power (indication) = airflow*pressure ratio 0.3*2=0.6 (Vacuum 0.75 * 1/0.2678 = 1.027)
The advantage of the pressure system is:
smaller pipe diameter
smaller sized air pump
less energy consumption per conveyed ton.
This is caused by the lower velocities in pressure conveying as a result of the denser air.
2)The pick up velocity in a vacuum system is calculated as:
Air flow/pipe area = Pump displacement*(1-vacuum)/(3.141593/4 * D^2)
The pick up velocity in a vacuum system (at the beginning of the pipe) is initially chosen as 6@7 times the suspension velocity and checked in the calculation.
Have a nice day
Teus ■
Teus
Fly Ash Pneumatic Conveying Problem
Recently , I visited a trial of fly ash pneumatic conveying.
Fly ash:
bulk dense 700kg/m^3,
particle diameter <=10um,
good fluidized .
Distance :
horizonal 410 m,
vertical 45 m
pipe bore: 80 mm,
and about 300 m distance to entry with pipe bore 100mm,
spherial bend: 19 ,
diameter : 240mm,
resource of pressure : 0.7MPa,
air pipe bore :50mm,
When conveying ,
flow rate is 4.5~6m^3/min, (normal)
Fly ash is discharged from top of silo, fluidized air entry into the bottom of silo, silo volume: 1.5m^3
when the pressure of silo is about 0.4Mpa, conveying starts , but in run , we find within 50m distance to entry of fly ash always jam.
Why ?
■