Re: Pilot Plant For Providing Ready Mix
Posted on
4. Dec. 2008 - 05:38
Don't fergit the gravel/ballast. You need a bag filling station to receive from 3 bins & 3 feeders. You set the feeders to deliver the proportions appropriate to the grade of your product and away you go. Why would you need a pilot plant? ■
Dry Mortar
Posted on
7. Dec. 2008 - 01:15
thanks for attention.
Don't fergit? the gravel/ballast?
I think its better to say "dry mortar", is it correct?
our raw material is cement and stone. I would like to know that commercially what they do to provide dry mortar from these primary materials: crushing? sizing(seive)? weighing hopper? packing? does it have any flowsheet such as cement plant?
meanwhile about the packing what should be the material of the bag?
thanks in advance
Masoomeh
FISTING AMATEUR ■
Pilot Plant for Providing Ready Mix
Dears,
I would like to design a pilot plant for providing ready mix included cement and sand,... ofcourse dry and fill it in the pocketswhich I have seen that in some country they sell it in the supermarkets and the users simply add water and provide concrete
is there any reference what:
1- percentage of cement and other material
2- the equipment normally we ashould have in this plant
we would pleased if someone give me some information for ths production: ready mix. meanwhile I am not sure that this is the correct word I have used for my purpose.
Best regards
Masoomeh