Problem in Ash Conveying

Posted in: , on 31. Aug. 2010 - 10:54

Dear Mr teus

expecting reply from u

I am working for an ash conveying system of a 25 MW power plant

It is dense phase pneumatic conveying (pulse type conveying)

My air receiver location i had kept was near to the ash collection points

client wants it to be 70 mtr away from plant at compressor room

I want to justify them for the location of reciver

Can u tell me the exact reason why we cant keep receiver location far away from vessel collecting point

Regards

Manthan

Re: Problem In Ash Conveying

Posted on 31. Aug. 2010 - 09:31

Dear Manthan,

Can you describe the system and the distance in that system that has to be (or not to be) increased.

Have a nice day

Teus