We are looking for Equipment supplier /turnkey contractors for hopper modification job at Kakinada Port site. The main scope of work shall be--

Numbers of hoppers to be modify--2

Total numbers of Grizzly under each hopper-2 (total grizzlies-4)

Cap. of each grizzly--750 tph

Total extraction from the hopper-1200-1250 tph from both the grizzlies.

Size of coal lumps +200 and below---95 %

Size of coal lumps +200 and above--5%(Max size of coal lumps--1200x200 mm)

Moisture contents--25% max.

Modification dwgs shall be provided to the contractor after finalization of grizzly suppliers.

For any other requirement please call 09811055650 or mail to www.libranengineering.com