Coal conveying problem

Posted in: , on 28. Sep. 2008 - 17:08

Dear Sirs,

We are facing problem in coal conveying to our precalciner.kindly advice to solve the problem.the following are the parameters.

30 TPH coal has to pumped to pre calciner.

total length of the pipe is 80 mtr

Dia of the pipe is 250mm

nu of 90 deg bend is 4 nos.

5580 cu.mtr/hr.

Pressure is 0.632kg/sq.cm

before FK pump line pressure without feed is 4000mmwc

FK pump model is SM-250

140X90 pitch

45 kw

1000rpm.

but frequent blockage of the pipe line lead the kiln stoppage.

kindly advice pl.

regards

V.Balakrishnan

Sagar Cements Limited,

AP.India