Re: Standards For Capacity Tests Of Belt Conveyors
Dear Mr. Serdar CAMDIBI,
I do not know about the standard defining the capacity testing procedure for conveyor.
However, this testing can be done based on following guidelines :
1) You have to see your purchase contract with your supplier. Anything mentioned about the capacity testing etc. in your contract will prevail.
2) The first step is to have a meeting with the representative of your supplier to fix date and time for testing and also testing modality.
3) Name of the people who will be conducting this test and who should be present during such test.
4) Method for taking the reading & creating record and joint signatures on the document.
5) General practice is to have testing period of either four hours or eight hours at a time etc. and also the number of days during which the testing is to be done. For a small conveyor a 4 hours test could be adequate. Such period will depend upon the daily operation of the plant (concerned section).
6) If supplier scope is only single conveyor and suppose you have decided to conduct the test for 4 hours then you have to make the necessary preparation to feed the conveyor for 4 hours as per agreed method. Also, the system ahead of the conveyor should be able to receive this material.
7) The checking for conveyor capacity is to be done appropriate to your equipment. In a regular belt conveying system, there are belt weighers. If your chain conveyor is located as a part of such system then you can make use of the reading of belt weighers. If all such facility is not there then people also do such testing in a crude manner that is the number of trucks arrived and their content weighment at weigh bridge etc.
I do not know about your total system, so I am not in a position to make more specific statement. However, I think the above information will enable you to plan and define your testing procedure. The complexity of such testing will depend upon the value of the equipment or plant. For a less value item obviously it will be very simple in nature but for a large value item / plant, the testing happens to be a major exercise, a project in weeks.
Regards,
Ishwar G Mulani.
Author of Book : Engineering Science and Application Design for Belt Conveyors.
Author of Book : Belt Feeder Design and Hopper Bin Silo
Advisor / Consultant for Bulk Material Handling System & Issues.
Email : parimul@pn2.vsnl.net.in
Tel.: 0091 (0)20 25882916 ■
Re: Standards For Capacity Tests Of Belt Conveyors
If U are looking at acceptance tests, perhaps u should think a bit more globally.
U should refer to the contract and technical specificastions and drawings for the bakground and basis for test regime.
Ideas include.
emergency stop functions - actual function and also no spillage nor overfilling of transfer chute
start loaded test
restart from blocked chute test
test of all blocked chute and belt drift sensors
belt alignment / tracking checks
motor and gearbox running temps, amps etc.
abnomral noise, vibrations etc
noise levels eg fast belts
number of restarts per hour on motor
braking distance checks
demand power checks wrt design
actual capacity as per your post
For Capacity > U will need a belt scale for your tests, or U could use bulk density and draw down from a hopper of known volume.
U could also stop the belt loaded and measure 1m of material on the belt > calculate/estimate effective tonnage rate.
Hope this helps
Cheers
James ■
Only Asking For Standards Or Regulations..
Thanks for your kindness..
We are working for a power plant of Energy Ministry of Turkiye.
We have two parallel lines of coal handling conveyors.
(%100 capacity of redundancy each)
now we are about to exacute the performance tests for temporary exceptance...
each lines should have the capacity of 600 ton/h.
We have a procedure to follow.
But there is chance to make revisions on it.
If you know any standard of the duration of tests, it is the most important part for us.
The Contractor says; it is a fact for them to exacute the tests for 5 minutes to 2 hours, from their past experiences.
we want to force them to the maximum duration that we can do,
because the system is not perfect.
If there is a standart or a regulation for these tests, we shall follow it.
Es-selam
Serdar CAMDIBI
Mech. Eng.
18 MART CAN TERMIK - 2x160MW CFB POWER PLANT -
ÇAN/ÇANAKKALE,TURKIYE
serdarch@mynet.com ■
Re: Standards For Capacity Tests Of Belt Conveyors
In my experience I have not come across any "standard" for acceptance trials.
" .. we want to force them to the maximum duration that we can do .. "
What was in the original contract? Are you trying to impose conditions retrospectively? You can't expect a contractor to do more than was specified.
If you wanted specific capacity checks it should have been stated in your contract document up front! ■
Re: Standards For Capacity Tests Of Belt Conveyors
Two conditions set the capacity for supplier warranties:
1. Weigh scale totalizer reading for a set time of (say 8 hours) that has sufficient power to deliver 600 t/h x hours x 8 hours = 4800 tons totalized. Of course the product stream feed rate should be controlled within a set amount. Product bulk density and variation in product stream must be allowed within a noted tolerance so that there is no spillage and there is sufficent power without compromising belt , idlers, and structures during running, starting and stopping for all load and weather conditions.
2. Belt edge clearance, at design tonnage -- must be within established guidelines to control against spillage either at the load station, at the transition discharge, or at vertical or horizontal curve sections. The edge clearance should include an allowance for product containment against spillage and includes variations in mistracking from :
a) belt internal construction deviation,
b) splice alignment deviations,
c) load station off-center loading (can be controlled by modern chute design),
d) product roll-back on inclines and declines which results in spills
e) product lump size sensitive to loading turbulence after skirts
f) variations in bulk density
g) comment from others ................ ■
Re: Standards For Capacity Tests Of Belt Conveyors
The specific point of my above comments is that sufficient operation time must pass to observe some reasonable level of variations which confirms that the design meets a standard against spillage. Most contractors must convey for 24 to 48 hours of continuous duty as the commisioning sign off.
The sign-off includes sufficient operating time to check mechanical and electrical equipment vibration, overheating, and other critical long term operational behaviors, as well as spillage given above. ■
Checking At The Time Of Taking Over
In addition to above following factors are very important for various conveyor components
0.0 Conveyor belt
Maximum tension of the belt at full load during starting and steady state condition
and actual available factor of safety of the belt
2.0Motor
Motor actual power consumption at Maximum load and factor of safty available
Temperature rise
Vibration level
3.0Pulley
Actual deflection of pulley shaft at full load
Temperature rise of Pulley Bearings
Vibration level of pulley bearings
4.0Actual speed of the belt compared to design speed
5.0Gear box
Actual factor of safety of gear box based on actual power consumption
Temperature rise of gear box
Vibration level of gear box
6.0Suitability of take-up unit
To start the conveyor at various loads
Availability of belt for at least one splice joint
7.0Suitability of chute design for following
No off center loading
Material degradation
No Chocking
Liners are positioned at all wearing pates
8.0Belt cleaners
Effectiveness of belt cleaners
9.0Skirt board
Check proper functioning of skirt rubbers
Above points may be checked as per terms of agreement between supplier and clint
A R SINGH ■
Standards for Capacity Tests of Belt Conveyors
Does anybody know a regulation about the Capacity Tests of Belt Conveyors?
We are about to execute the temporary acceptance of belt conveyors in our coal handling system. However, we don't know a way to consider how the tests should be carried on.
Is there a Standard for capacity test of conveyors please inform us.
Serdar CAMDIBI
Mech.Eng.
18 MART CAN TERMIK - POWER PLANT
CAN / CANAKKALE-TURKIYE
tel :+90-286-4353370 (internal:1059)
fax:+90-286-4353375
e-mail : serdarch@mynet.com ■